Progress Update 3/18/2019

World class learning is the foundation on which we build our futures; and building foundations are officially underway at Hammond Creek Middle School.

Progress Update:

  • Excavation and layout for the foundation on classroom wing 800 is underway.

  • Storm pipe installation continues on the east and west side of the building.

  • The ball field area is currently being brought up to grade.