Progress Update 3/29/2019

·       Job trailer delivered and set up.

·       Power pending final connection.

·       Excavation and layout for footings on classroom wing 800 is underway.

·       Storm pipe installation continues on the east and west side of the building.

·       Ball field is being brought up to grade.

·       First footings pour to start this week on classroom wing 800.