Progress Update 5/10/2019

The following progress has been made:

·       All slabs for classroom room wings have been poured

·       Masonry walls have been started for classroom wing 700

·       Wall rough in plumbing is complete in wing 800

·       Wall rough in underway on wing 700 and 600

·       Storm system install is ongoing

·       Retaining wall at southwest side of property has been completed

·       Footings and foundation block underway for the kitchen and cafeteria

 

·